Memo report
To: Board of directors (Leatty Shanghai)
From: Nikolay Gitsov (Project Manager for Leatty Shanghai)
Date: 16 December 2011
Subject: Leatty Shanghai Rescue Strategy
Introduction
On Friday, 16 December 2011, the project manager discussed strategic decisions and actions for a change in the current situation about rescuing the project. Problems such as cost overruns, schedule delays, bad communication and bad teamwork are of great importance for the project. Strategy and actions are needed urgently. We agreed on the following changes.
Information exchange and co-ordination of tasks
The problem of information exchange is our main concern at this point. Firstly, we agreed on video conference schedule which will be comfortable for both parties. Skypetm software will be used and every participant will get a manual with instructions. Secondly, areas of responsibility will be introduced. In this way we will improve communication flow between individuals and departments as well as avoid tasks overlap.
Communication, morale and working practices
At the meeting, we agreed that onsite meeting will be held. All interested parties will be present and important issues concerning the execution of the project will be discussed. We will introduce a bonus reward system for overtime work. Furthermore, human resources specialist will be working onsite with the people. His task will be related to establishment of better teamwork. The managers will receive an additional training concerning real evaluation and feedback. People will talk free for the problems encountered, which will improve communication.
Safe atmosphere
We agreed on creating outside activities for workers such as family dinners and parties. In this way people can introduce their families and talk freely with managers and executive staff about problems and risks related to the project.
Lessons learnt
We agreed that in the first part of the project development, there were a lot of issues and misunderstandings. With actions and strategy discussed on the meeting we will achieve better communication flow, improve teamwork, establish trust among the staff, share problems and discuss risks. Furthermore, we will reduce delays in the building schedule, tasks overlap and problems with supply chain.
Next meeting schedule
Date: 9th January 2012
Time: 10:00h (Local time)
Place: Leatty construction site, Shanghai
Nikolay Gitsov
Project manager, Leatty